The Royal Navy’s Newest Nightmare: It Built Its Frigates the Wrong Way, nationalinterest.org

Earlier this month, it was revealed that the first two of the senior service’s much-hyped Type 31 Inspiration-class frigates, meant to be the workhorses of the fleet, had been assembled out of sequence. That isn’t a simple misunderstanding, either. It has resulted in months of delays, with the costs expected to be as high as £140 million ($187 million) to rectify.

“During the outfitting stage we have experienced higher-than-expected levels of rework as a result of design changes and the long-term impacts of out-of-sequence build activity earlier in the program,” shipbuilder Babcock acknowledged.

“Whilst the number of such rework events is not entirely unexpected, the work is being performed in the later stages of completion and therefore is more complex and more costly,” Babcock added. The company didn’t explain exactly how the issue came to be. Läs artikel